Component | Outcome measures | Details |
---|---|---|
Training | Adopted | Implemented in all PHCs. Some professionals were not trained because they were absent or worked on other duties on the training date |
Flowcharts | Partially adopted Low fidelity | Flowcharts were used in all PHCs, but risk screening was partially implemented. Indication of serology was increased without using risk assessment |
Reminders | Adopted | Reminder posters were used in all centres |
Frequently asked questions sheet | Not adopted | Few informants mentioned knowing or having used this component |
Register of at-risk persons and positive cases | Poorly adopted Low fidelity Low feasibility | No registers of persons at risk were implemented and, registers of positive cases were used in only one PHC. Clinical records of positive patients were labeled |
Management facilitators | Partially adopted Low fidelity Low feasibility | All PHCs appointed facilitators, but their performance and commitment were variable |